Dear Readers, Welcome to Tunnel Engineering Objective Questions have been designed specially to get you acquainted with the nature of questions you may encounter during your Job interview for the subject of Tunnel Engineering MCQs. These objective type Tunnel Engineering questions are very important for campus placement test and job interviews. As per my experience good interviewers hardly plan to ask any particular question during your Job interview and these model questions are asked in the online technical test and interview of many IT & Non IT Industries.
a) carrying water
b) non-cohesive soils
c) tunnels driven by shield method
d) placement of concrete lining
Ans: d
1. drilling and blasting
2. timbering
3. pumping
4. mucking
Select the correct answer usiny the codes given below Codes :
a) 1,2,3,4
b) 1,4,2,3
c) 2,1,4,3
d) 2,4,1,3
Ans: b
a) normal to face
b) inclined at 45° to the face
c) inclined at 15° to the face
d) inclined at 30° to the face
Ans: b
a) remains same
b) decreases
c) increases by 2.25 times
d) increases by 3.5 times
Ans: c
(i) shot drill
(ii) diamond drill
(iii) wagon drill
(iv) churn drill Of these statements
a) (i) and (ii) are correct
b) (iii) and (iv) are coiTect
c) (i) and (iv) are correct
d) (ii) and (iii) are correct
Ans: b
a) only up holes
b) only down holes
c) horizontal or up holes
d) horizor„al, down or up holes
Ans: d
a) 2N
b) N + 2
c) 2 N + 1
d) 2 N + 2
Ans: d
a) wagon drill, churn drill, shot drill
b) wagon drill, shot drill, churn drill
c) shot drill, churn drill, wagon drill
d) churn drill, wagon drill, shot drill
Ans: a
a) propelling jacks
b) liner plate
c) hood
d) tail
Ans: b
a) 6 mJ per second per m2 of face area
b) 6 m3 per minute per m2 of face area
c) 20 m3 per minute per m2 of face area
d) 6 m3 per hour per m2 of face area
Ans: b
Reason R : In English method of tunneling, the masons and excavators have to work alternately.
Select your answer based on the coding system given below :
a) Both A and R are true and R is the correct explanation of A.
b) Both A and R are true and R is not the correct explanation of A.
c) A is true but R is false.
d) A is false but R is true.
Ans: a
i) is suitable for large sized tunnels
ii) is no,' suitable for railway or highway tunnel's
iii) requires heavy timbers Of these statements
a) only (i) is correct
b) (i) and (iii) are correct
c) (ii) and (iii) are correct
d) (i) and (ii) are correct
Ans: a
a) stone masonry
b) timber
c) cast iron
d) cement concrete
Ans: c
a) 42 D
b) 82 D
c) 104 D
d) 124 D
Ans: b
a) Needle beam method
b) Army method
c) German method
d) Italian method
Ans: b
a) 2 m
b) 3 m
c) 4 m
d) 5 m
Ans: b
a) silt
b) sand
c) clay
d) gravel
Ans: c
(i) is suitable for soils in which roof can stand for few minutes without support
(ii) is suitable for brick lining
(iii) is suitable for concrete lining
(iv) requires large number of trench jacks Of these statements
a) only (i) is correct
b) (i), (ii) and (iv) are correct
c) (i), (iii) and (iv) are correct
d) (i) and (ii) are correct
Ans: b
a) Army method
b) Needle beam method
c) Austrian method
d) English method
Ans: c
a) construction of side walls is completed before invert and roof arch are built.
b) construction of roof arch is completed before side walls and invert are built.
c) construction of invert is completed before side walls and roof arch are built.
d) construction of invert and side walls is completed before roof arch is built.
Ans: b
1. marking tunnel profile
2. loading explosives and blasting
3. checking misfire
4. mucking
5. removing foul gas
6. setting up and drilling
7. guniting
Select the correct answer using the codes given below.
Codes:
a) 1,6,5,3,4,2,7
b) 1,2,6,3,5,4,7
c) 1, 6,2, 5,4, 3, 7
d) 1,6,2,5,3,4,7
Ans: d
a) soft grounds
b) rock
c) self supporting grounds
d) broken grounds
Ans: b
1. Soil is soft.
2. Volume of existing surface traffic on the alignment is heavy.
3. Track is at a deeper level.
4. Water table is high.
In the construction of Metro Railways, "Cut and Cover" method of construction is suitable in situations listed at
a) 1 and 2
b) 1 and 3
c) 1 and 4
d) 2 and 3
Ans: c
a) It is suitable for construction in unstable rocks.
b) In this method, it is easy to install timber support.
c) Tunnelling can be continuous and the work can be expedited.
d) In case of excessive water, it is easy to take correct steps.
Ans: c
a) removal of bottom portion
b) excavation of one drift in the centre
c) removal of top portion
d) excavation being done along the periphery
Ans: d
a) liner plate
b) trench jack
c) stiffener
d) cutting edge
Ans: d
Reason R : A tunnel through rock, hard or soft, does not need any concrete lining.
Select your answer based on the coding system given below:
a) Both A and R are true and R is the correct explanation of A.
b) Both A and R are true but R is not the correct explanation of A.
c) A is true but R is false.
d) A is false but R is true.
Ans: c