1. PERT technique of network analysis is mainly useful for _____.
small projects
large and complex projects
research and development projects
deterministic activities
2. Select the correct statement.
Activity arrows in a CPM network are drawn to scale
The tail of an arrow represents the finish of an activity
Arrow bead represents the start of an activity
none of the above
3. Which of the following is a weakness of bar chart ?
interdependencies of activities
project progress
uncertainties
all of the above
4. Which of the following is not a PERT event ?
site investigation started
sessional work completed
bus starts from Jaipur
class is being attended
5. In PERT analysis, the time estimates of activities and probability of their occurrence follow
normal distribution curve
Poisson's distribution curve
Beta - distribution curve
none of the above
6. The area under the Beta - distribution curve is divided into two equal parts by
most likely time
optimistic time
pessimistic time
expected time
7. Which of the following does not represent an activity?
site located
foundation is being dug
the office area is being cleaned
the invitations are being sent
8. Earliest finish of an activity is always
greater than earliest event time of the following node
less than earliest event time of the following node
less than or equal to earliest event time of the following node
greater than or equal to earliest event time of the following node
9. Select the incorrect statement.
Earliest start of an activity is the early event time of the node it leaves.
Latest finish of an activity is the late event time of the node it enters.
Latest start of an activity is its latest finish minus its duration.
none of the above
10. Latest start of an activity is always _____.
greater than or equal to latest event time of preceding node
less than or equal to latest event time of preceding node
equal to latest event time of preceding node
less than latest event time of preceding node
11. Select the incorrect statement.
Start float and finish float are always equal.
Total float can be either start float or finish float.
Start float and finish float need not be equal.
Start float and finish float are the differences between activity times and not event times.
12. Free float is mainly used to ______.
identify the activities which can be delayed without affecting the total float of preceding activity
identify the activities, which can be delayed without affecting the total float of succeeding activity
establish priorities
identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities
13. Whenever an activity has zero total float, then ______.
free float of the activity must be zero but independent float need not be zero
independent float must be zero but free float need not be zero
free float and independent float both must be zero
free float and independent float both need not be zero
14. Total float for any activity is defined as the difference between
its latest finish time and earliest start time for its successor activity
its latest start time and earliest start time
its latest start time and earliest finish time
its earliest finish time and earliest start time for its successor activity
15. Select the incorrect statement.
A critical path always begins at the very first event.
A critical path always terminates at the last event.
Critical activities control the project duration.
Critical activity is the one for which free float is zero.
16. Free float for any activity is defined as the difference between
its earliest finish time and earliest start time for its successor activity
its latest start time and earliest start time
its latest finish time and earliest start time for its successor activity
its earliest finish time and latest start time for its successor activity
17. Critical path ______?
is always longest
is always shortest
may be longest
may be shortest
18. The independent float affects only ______.
preceding activities
succeeding activities
the particular activity involved
none of the above
19. A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be
15 minutes
20.143 minutes
21 minutes
27 minutes
20. What estimate would you give for the variance in above problem ?
81
54
36
9
Top IT Interview Questions And Answers
Top SAP Analytics Cloud Interview Questions Answers
100+ TOP C++ LAB VIVA Questions and Answers
100+ TOP Compiler Design Interview Questions and Answers
100+ TOP SYSTEM Programming LAB VIVA Questions and Answers
200+ TOP COMPUTER NETWORKING Interview Questions and Answers
100+ TOP ZENER DIODE LAB VIVA Questions and Answers
MOBILE COMMUNICATION Multiple Choice Questions
TOP 100+ Computer Graphics Multiple Choice Questions
Read More
Top MCQS Questions And Answers
Writing for Academic and Professional Success Objective Questions
100+ TOP Building Construction Multiple choice Questions and Answers
Antenna and Wave Propagation MCQ Questions and Answers
TOP 100+ Embedded Processors Multiple choice Questions
TOP 100+ Internet Multiple choice Questions and Answers
100+ TOP Engineering Drawing Multiple choice Questions
TOP 150+ ETO Multiple choice Questions and Answers
Biomedical Engineering Multiple choice Questions & Answers
Read More
Top Medical Questions And Answers
TCA Cycle Interview Questions & Answers
RNA Structure Interview Questions & Answers
Spleen Surgery Interview Questions & Answers
poxviridae And picornaviridae Interview Questions & Answers
Wine And Beer Interview Questions & Answers
Vitamins and Coenzymes Interview Questions & Answers
Viruses In Eukaryotes Interview Questions & Answers
Virus Interview Questions & Answers
Read More
Top Engineering Questions And Answers
100+ TOP METALLURGY ENGINEERING Interview Questions and Answers
200+ TOP MECHANICAL Engineering Interview Questions and Answers
100+ TOP AIRPORT Engineering Interview Questions and Answers
EDC Lab Viva Questions and Answers
Epidemiology Multiple choice Questions & Answers
SAP Hybris Interview Questions & Answers
Power BI Interview Questions & Answers
Process Instrumentation and Control Interview Questions
Read More
Top Quiz Questions And Answers
Highway Engineering Online Quiz Questions
Environmental Engineering Online Quiz Questions Answers
Engineering Mechanics Online Quiz Questions
Design of Steel Structures Online Quiz Questions Answers
Construction Planning and Management Quiz Questions
Applied Mechanics and Graphics Online Quiz Questions
Fluid Mechanics Online Quiz Questions
Airport Engineering Quiz Questions & Answers
Read More
TOP Interview Questions and Answers
TypeScript Interview Questions
SAP Hybris Interview Questions
Blue Prism Interview Questions
Joomla Interview Questions
RPA Interview Questions
SAP ABAP Interview Questions
Graphic Designer Interview Questions
WebSphere Interview Questions
TOP Engineering Questions
Airport Engineering Questions
Circuit Design Interview Questions
Electrical Cables Interview Questions
Engineering Mechanics Questions
Fluid Mechanics Interview Questions
Irrigation Engineering Questions
Induction Motor Interview Questions
Thermodynamics Interview Questions
Best Medical Interview Questions
Anatomy Interview Questions
Bio-Chemistry Interview Questions
Bio-Technology Interview Questions
Cardiologist Interview Questions
Dental Interview Questions
Immunology Interview Questions
Neurology Interview Questions
Nutrition Interview Questions
© All right Reversed.
Latest Interview Questions