Dear Readers, Welcome to SAP PS Objective Questions and Answers have been designed specially to get you acquainted with the nature of questions you may encounter during your Job interview for the subject of SAP PS Multiple choice Questions. These Objective type SAP PS are very important for campus placement test and job interviews. As per my experience good interviewers hardly plan to ask any particular question during your Job interview and these model questions are asked in the online technical test and interview of many IT & Non IT Industry.
a. Controlling Area & Company Code assignments is mandatory at Project Definition level.
b. Currency can be changed Only if the controlling area does not allow different company code currencies.
c. Business area assignment is mandatory at Project Definition level.
d. Profit center assignment is mandatory at Project Definition level.
Answer: a, b
a. Business Area Currency
b. Controlling area currency
c. Object Currency
d. Transaction currency
Answer: b, c, d
a. True
b. False
Answer: B
a. Persons
b. Organizational units
c. Jobs
d. Positions
Answer: a, b, d
a. In Customizing for the Project System, you must have defined profiles for workforce planning in Resources.
b. Assigned work centers to the internally processed activities.
c. Assigned one or more labor capacity to a work center.
Answer: a, b
a. Controlling Area
b. Controlling Area and Company Code
c. Controlling Area and Plant
d. Controlling Area, Company Code and Proj Currency
Answer: a
a. CNEX0009 -- EXIT_SAPLCOMK_001
b. CNEX0011 -- EXIT_SAPLCOMK_002
c. CNEX0015 -- EXIT_SAPLCN10_002
d. CN015AFZ -- EXIT_SAPLCNFZ_003
Answer: a, b, c
a. 9999 components may be created per network.
b. Project System supports consignment stock.
c. Component scrap is considered during BOM explosion.
Answer: A
a. Yes
b. No
Answer: A
a. 999
b. 256
c. 99
d. 255
Answer: D