Dear Readers, Welcome to Construction Planning and Management Objective Questions have been designed specially to get you acquainted with the nature of questions you may encounter during your Job interview for the subject of Construction Planning and Management MCQs. These objective type Construction Planning and Management questions are very important for campus placement test and job interviews. As per my experience good interviewers hardly plan to ask any particular question during your Job interview and these model questions are asked in the online technical test and interview of many IT & Non IT Industries.
a) small projects
b) large and complex projects
c) research and development projects
d) deterministic activities
Ans: c
a) Activity arrows in a CPM network are drawn to scale
b) The tail of an arrow represents the finish of an activity
c) Arrow bead represents the start of an activity
d) none of the above
Ans: d
a) interdependencies of activities
b) project progress
c) uncertainties
d) all of the above
Ans: d
4. In the network shown in Fig. , activity 4-5 can be started only when
a) activity 3 - 4 is completed
b) activity 2 - 4 is completed
c) activity 2 - 3 is completed
d) activity 2 - 4 and 2 - 3 both are completed
Ans: d
a) site investigation started
b) sessional work completed
c) bus starts from Jaipur
d) class is being attended
Ans: d
a) normal distribution curve
b) Poisson's distribution curve
c) Beta - distribution curve
d) none of the above
Ans: c
a) most likely time
b) optimistic time
c) pessimistic time
d) expected time
Ans: d
a) 1, 2,3, 4, 5, 6 and 7 respectively
b) 1, 3,2,4, 5,6 and 7 respectively
c) 1,2, 3, 5, 6,4 and 7 respectively
d) 1, 3,2, 5, 6,4 and 7 respectively
Ans: b
a) Events 3 and 4 occur after event 2.
b) Event 7 can occur after event 4.
c) Event 7 precedes event 6.
d) Event 5 follows event 3.
Ans: b
a) 1-2 and 4-7
b) 2-3 and 1-2
c) 2-3 and 4-7
d) 1-2 and 3-6
Ans: b
a) site located
b) foundation is being dug
c) the office area is being cleaned
d) the invitations are being sent
Ans: a
a) greater than earliest event time of the following node
b) less than earliest event time of the following node
c) less than or equal to earliest event time of the following node
d) greater than or equal to earliest event time of the following node
Ans: c
a) Earliest start of an activity is the early event time of the node it leaves.
b) Latest finish of an activity is the late event time of the node it enters.
c) Latest start of an activity is its latest finish minus its duration.
d) none of the above
Ans: d
a) 7
b) 8
c) 9
d) 5
Ans: c
a) greater than or equal to latest event time of preceding node
b) less than or equal to latest event time of preceding node
c) equal to latest event time of preceding node
d) less than latest event time of preceding node
Ans: a
a) 2
b) 4
c) 8
d) 7
Ans: b
a) activity 4 - 6 is completed
b) activity 3 - 5 is completed
c) activity 2 - 3 is completed
d) both activities 2 - 3 and 4 - 6 are completed
Ans: d
a) expected time of activity A is greater than the expected time of activity B
b) expected time of activity B is greater than the expected time of activity A
c) expected time of both activities A and B are same
d) none of the above
Ans: c
a) 3.5 and 5/6
b) 5 and 25/36
c) 3.5 and 25/36
d) 4 and 5/6
Ans: c
a) Start float and finish float are always equal.
b) Total float can be either start float or finish float.
c) Start float and finish float need not be equal.
d) Start float and finish float are the differences between activity times and not event times.
Ans: c
a) identify the activities which can be delayed without affecting the total float of preceding activity
b) identify the activities, which can be delayed without affecting the total float of succeeding activity
c) establish priorities
d) identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities
Ans: b
a) free float of the activity must be zero but independent float need not be zero
b) independent float must be zero but free float need not be zero
c) free float and independent float both must be zero
d) free float and independent float both need not be zero
Ans: c
a) its latest finish time and earliest start time for its successor activity
b) its latest start time and earliest start time
c) its latest start time and earliest finish time
d) its earliest finish time and earliest start time for its successor activity
Ans: b
a) 0
b) 1
c) 2
d) none of the above
Ans: b
a) 1-2-3-4-5-6
b) 1-2-4-5-6
c) 1-2-3-5-6
d) 1-2-4-3-5-6
Ans: a
a) A critical path always begins at the very first event.
b) A critical path always terminates at the last event.
c) Critical activities control the project duration.
d) Critical activity is the one for which free float is zero.
Ans: d
a) its earliest finish time and earliest start time for its successor activity
b) its latest start time and earliest start time
c) its latest finish time and earliest start time for its successor activity
d) its earliest finish time and latest start time for its successor activity
Ans: a
a) is always longest
b) is always shortest
c) may be longest
d) may be shortest
Ans: a
a) preceding activities
b) succeeding activities
c) the particular activity involved
d) none of the above
Ans: c
a) 15 minutes
b) 20.143 minutes
c) 21 minutes
d) 27 minutes
Ans: c
a) 81
b) 54
c) 36
d) 9
Ans: a
a) total float
b) free float
c) interfering float
d) independent float
Ans: d
a) crash time
b) normal time
c) optimistic time
d) standard time
Ans: b
a) crash time
b) normal time
c) optimistic time
d) between normal time and crash time
Ans: d
a) minimum
b) maximum
c) zero
d) infinite
Ans: a
a) decreasing the direct cost and increasing indirect cost
b) increasing the direct cost and decreasing the indirect cost
c) increasing the direct cost and indirect cost both
d) decreasing the direct cost and indirect cost both
Ans: b
a) cheapest critical activity
b) cheapest non-critical activity
c) costliest critical activity
d) costliest non-critical activity
Ans: a
a) resource levelling
b) resource smoothening
c) updating
d) critical path scheduling
Ans: c
a) an activity
b) an event
c) both event and activity
d) none of the above
Ans: b
a) 9 days
b) 13 days
c) 14 days
d) 19 days
Ans: c
a) resources
b) project duration time
c) both resources and project duration time
d) none of the above
Ans: b
a) change of critical path
b) decrease of project completion time
c) increase of project completion time
d) all of the above
Ans: d
a) normal durations for all the activities
b) crash durations for all activities
c) crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
d) crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities.
Ans: d
a) total float and free float
b) total float and independent float
c) free float and independent float
d) none of the above
Ans: a
Reason (R) : Earliest finish time and latest finish time for events 5-7 are same Select the correct answer.
a) A is correct but R is not correct
b) R is correct but A is not correct
c) both A and R are correct
d) both A and R are incorrect
Ans: a
a) reduce by 200 kg
b) increase by 200 kg
c) increase by 250 kg
d) reduce by 250 kg
Ans: a
a) Drag line
b) Hoe
c) Clam shell
d) Dipper shovel
Ans: d
a) Drag line
b) Hoe
c) Clam shell
d) Dipper shovel
Ans: a
(i) Mast
(ii) Boom
(iii) Bull wheel
(iv) Jack
Of these statements
a) (i), (ii) and (iv) are correct
b) (ii), (iii) and (iv) are correct
c) (i), (iii) and (iv) are correct
d) (i), (ii) and (iii) are correct
Ans: d
a) Moist loam
b) Good common earth
c) We|l blasted rock
d) Wet sticky clay
Ans: a
a) Moist loam
b) Sand and gravel
c) Good common earth
d) Wet sticky clay
Ans: d
(i) Output can be increased by reducing the angle of swing for a given depth of cut.
(ii) For a given angle of swing, output will be maximum at optimum depth of cut.
(iii) Output can be increased by keeping the depth of cut less than optimum depth,
(iv) Output can be increased by increasing the size of shovel. Of these statements
a) (ii), (iii) and (iv) are correct
b) (i), (ii) and (iv) are correct
c) (i), (iii) and (iv) are correct
d) (i) and (iv) are correct
Ans: b
Reason R: If the angle of swing is decreased, the cycle time will be decreased.
Select the correct answer.
a) Both A and R are true and R is the correct explanation of A.
b) Both A and R are true but R is not the correct explanation of A.
c) A is true but R is false.
d) A is false but R is true.
Ans: a
a) equal to X
b) more than X
c) less than X
d) any of the above
Ans: c
(i) increased if drawbar HP of the tractor is increased for a given hauling distance
(ii) decreased if drawbar HP of the tractor is increased for a given hauling distance
(iii) increased if the hauling distance is increased for a given drawbar HP of the tractor
(iv) decreased if the hauling distance is increased for a given drawbar HP of the tractor Of these statement
a) (i) and (iii) are correct
b) (i) and (iv) are correct
c) (ii) and (iii) are correct
d) (ii) and (iv) are correct
Ans: b
a) Rs. 4,75,000/-
b) Rs. 5,75,000/-
c) Rs. 6,50,000/-
d) Rs. 8,50,000/-
Ans: b
a) Rs. 8,43,750/-
b) Rs. 8,75,000/-
c) Rs. 10,50,000/-
d) Rs. 11,56,250/-
Ans: a
a) 500 cum
b) 1000 cum
c) 1500 cum
d) 2000 cum
Ans: a
a) Ice
b) Concrete
c) Loose sand
d) Earth
Ans: d
(i) Vehicle load
(ii) Grade
(iii) Ground conditions Of these statements
a) only (i) is correct
b) (i) and (ii) are correct
c) (i) and (iii) are correct
d) (ii) and (iii) are correct
Ans: c
a) Concrete
b) Loose sand
c) Asphalt
d) Firm earth
Ans: b
a) 30 kg
b) 300 kg
c) 900 kg
d) 1000 kg
Ans: c
a) 2 kg/tonne
b) 6 kg/tonne
c) 9 kg/tonne
d) 20 kg/tonne
Ans: c
a) 10000 kg
b) 12500 kg
c) 22500 kg
d) 5000 kg
Ans: b
a) 20 kg/tonne
b) 30 kg/tonne
c) 40 kg/tonne
d) 50 kg/tonne
Ans: c
a) Rs. 31050
b) Rs. 34500
c) Rs. 37950
d) Rs. 50000
Ans: a
a) Rs.1740
b) Rs.3480
c) Rs.5220
d) Rs.6960
Ans: b
a) 50%
b) 84.1%
c) 99.9%
d) 100%
Ans: a
a) 50%
b) less than 50%
c) more than 50%
d) 100%
Ans: c
a) 4 days
b) 6 days
c) 10 days
d) 16 days
Ans: d
a) 2.3% and 84.1%
b) 97.7% and 84.1%
c) 97.7 % and 15.9%
d) 15.9% and 97.7%
Ans: a
a) 3.7 years
b) 4.23 years
c) 5 years
d) 7.87 years
Ans: b
1. interdependence of the operations cannot be portrayed.
2. progress of work can be measured.
3. spare time of the activities can be determined.
4. schedule cannot be updated.
Of these statements
a) 1,2 and 3 are correct
b) 1 and 4 are correct
c) 2, 3 and 4 are correct
d) 1,2 and 4 are correct
Ans: b
1. greater than Total Float.
2. greater than Independent Float
3. equal to Total Float.
4. less than Independent Float. Of these statements
a) 1 and 4 are correct
b) 2 and 3 are correct
c) 1 and 4 are correct
d) 1 and 2 are correct
Ans: b
a) on all the activities
b) on all the activities lying on the critical path
c) only on activities lying on the orginal critical path and having flatter cost slopes
d) on original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope
Ans: d
a) increase in rates of only important materials
b) variation in cost in materials element, labour element and petrol-oil-lubricant element
c) variation in total cost of the project on an ad hoc basis
d) rate of inflation
Ans: b
a) measurement of risks to eliminate failures
b) applying the theory' of probability to sample testing or inspection
c) reduction in wastage of inspection costs
d) reduction in costs for the removal of defects
Ans: b
a) Yes, because of heavier overheads and handling cost
b) Yes, because of the very high order of quality control for the factory made components
c) No, because of repetitive manufacture of a number of elements
d) No, because of savings in site labour
Ans: c
a) on commencement of work at site for payment of loan taken by him
b) for the purchase of construction materials
c) for the payment of advances to labour and other staff
d) for all activities required to start the work at site on finalization of the contract document [ES 94]
Ans: d
a) the fund for rebuilding a structure when its economic life is over
b) raised to meet maintenance costs
c) the total sum to be paid to the municipal authorities by the tenants
d) a part of the money kept in reserve for providing additional structures and structural modifications [ES 94]
Ans: a
a) should invest in neither of the two projects
b) could invest in either of the two projects
c) should invest in project A
d) should invest in project B
Ans: a
a) total duration of project is reduced
b) total duration of project is increased
c) uniform demand of resources is achieved
d) cost of project is controlled
Ans: c
a) Rs. 8,800/-
b) Rs. 7,600/-
c) Rs. 6,400/-
d) Rs. 5,000/-
Ans: c
1. Projects are of the non-repetitive type.
2. Time required need not be known.
3. Time required is known precisely.
4. Events have been established for planning.
5. Emphasis is given to activities of project.
PERT is preferred for planning because of
a) 1,2 and 4
b) 3,4 and 5
c) 1,3 and 4
d) 1,2 and 5
Ans: a
1. Concreting of roof slabs
2. Brick-jelly lime concrete terracing
3. Erection of formwork for slab
4. Construction of parapet wall in terrace
The correct sequence of these activities is
a) 1,3,2,4
b) 3,1,4,2
c) 3,1,2,4
d) 1,3,4, 2
Ans: c
1. Drilling
2. Blasting
3. Mucking
4. Placing steel
5. Placing concrete
The correct sequence of these operations in tunnel construction is
a) 1,2,4,3,5
b) 1,3,2,4,5
c) 1,2,3,4,5
d) 1,3,4,2,5
Ans: c
a) 8 days
b) 9 days
c) 10 days
d) 15 days
Ans: b
a) 3425 kg
b) 5515 kg
c) 4350 kg
d) 2975 kg
Ans: b
a) trimming and finishing
b) shaping and trimming
c) finishing and shaping
d) finishing, shaping and trimming
Ans: d
a) Bulldozer
b) Clam shell
c) Scraper
d) Dump truck
Ans: d
a) Smooth-wheeled rollers
b) Vibratory rollers
c) Sheep foot rollers
d) Tampers
Ans: c
a) Hoe
b) Shovel
c) Dragline
d) None of the above
Ans: a
a) Kneading
b) Pressing
c) Tamping
d) Vibration
Ans: a
a) controlling the total quantity at each batch
b) weighing accurately, the quantity of each material for a job before mixing
c) controlling the quantity of each material into each batch
d) adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch
Ans: c
Wheeled tractors are replacing crawler tractors because
1. wheeled tractors travel faster.
2. crawler tractors are more expensive.
3. track parts of a crawler wear out quickly.
4. crawler tractors have stick control.
Of these statements
a) 1,3 and 4 are correct
b) 2, 3 and 4 are correct
c) 1,2 and 3 are correct
d) 1, 2 and 4 are correct
Ans: c
a) 80 and 90
b) 90 and 80
c) 85 and 75
d) 75 and 83
Ans: d
a) comparison of profit and loss
b) comparison of assets and liabilities
c) change in output due to change in input
d) economics of cost and benefits of the project
Ans: c
a) longest duration
b) highest cost slope
c) least cost slope
d) shortest duration
Ans: c
a) the detailed estimated cost based on detailed design
b) the several alternatives of the project that have been considered
c) the soil survey, traffic survey, concept design and approximate cost
d) the contract documents for inviting tenders
Ans: c