Dear Readers, Welcome to Economics of Power Generation Objective Questions have been designed specially to get you acquainted with the nature of questions you may encounter during your Job interview for the subject of Economics of Power Generation MCQs. These objective type Economics of Power Generation questions are very important for campus placement test and job interviews. As per my experience good interviewers hardly plan to ask any particular question during your Job interview and these model questions are asked in the online technical test and interview of many IT companies.
(a) maximum demand/average load
(b) average load x maximum demand
(c) average load/maximum demand
(d) (average load x maximum demand)172
Ans: c
(a) equal to unity
(b) less than unity
(c) more than unity
(d) equal to zero Diversity factor is always
Ans: b
(a) 10 to 15%
(b) 30 to 40%
(c) 50 to 60%
(d) 60 to 70%
Ans: a
(a) sinkingfund method
(b) straight line method
(c) both (a) and (b)
(d) none of the above
Ans: c
(a) thermal plant
(b) diesel plant
(c) hydroelectric plant
Ans: a
(a) average load/maximum load
(b) maximum demand/connected load
(c) connected load/maximum demand
(d) average load x maximum load
Ans: b
(a) cost of generation per unit power is increased
(b) total plant capacity is utilised for most of the time
(c) total plant capacity is not properly utilised for most of the time
(d) none of the above
Ans: b
(a) average power used during the period
(b) average kWh (kW) energy consumption during the period
(c) either of the above
(d) none of the above
Ans: b
(a) load survey method
(b) statistical methods
(c) mathematical method
(d) economic parameters
(e) all of the above
Ans: e
(a) the capital cost divided by number of year of life
(b) the capital cost minus the salvage value, is divided by the number of years of life
(c) increasing a uniform sum of money per annum at stipulated rate of in¬terest
(d) none of the above
Ans: b
(a) flat rate tariff
(b) two part tariff
(c) maximum demand tariff
(d) any of the above
Ans: c
(a) fixed charges
(b) operating or running charges
(c) both (a) and (b)
(d) either (a) or (b)
Ans: b
(a) dependent upon the energy consumed
(b) dependent upon the maximum demand of the consumer
(c) both (a) and (b)
(d) neither (a) nor (b)
Ans: b
(a) Peak load plant
(b) Base load plant
(c) Nuclear power plant
(d) Hydro electric plant
Ans: a
(a) average demand
(b) energy consumed
(c) maximum demand
(d) none of the above
Ans: b
(a) diesel engine
(b) hydraulic turbine
(c) gas turbine
(d) steam turbine
(e) any of the above
Ans: e
(a) fixed cost of unit generated
(b) running cost of unit generated
(c) both (a) and (b)
(d) neither (a) nor (b)
Ans: a
(a) nuclear power plant
(b) hydro power plant
(c) diesel power plant
(d) both (b) and (c)
(e) none of the above
Ans: d
(a) Nuclear
(b) Hydro
(c) Thermal
(d) Diesel
Ans: b
(a) equal to unity
(b) less than unity
(c) more than unity
(d) none of the above
Ans: c
(a) operating schedule of generating units
(b) sizes of generating units
(c) total installed capacity of the plant
(d) all of the above
Ans: d
(a) zero slope
(b) positive slope
(c) negative slope
(d) any combination of (a), (b) and (c)
Ans: d
(a) fixed charges
(b) semi-fixed charges
(c) running charges
(d) all of the above
Ans: d
(a) the greatest of all "short time interval averaged" demand during a period
(b) instantaneous maximum value of kVA supplied during a period
(e) both (a) or (b)
(d) none of the above
Ans: a
(a) sinking fund depreciation
(b) straight line depreciation
(c) reducing balances depreciation
(d) none of the above
Ans: a
(a) sinking fund depreciation
(b) straight line depreciation
(c) reducing balances depreciation
(d) none of the above
Ans: c
(a) less number of consumers
(b) more number of consumers
(c) neither (a) nor (b)
(d) either (a) or (b)
Ans: b
(a) positive
(b) negative
(c) zero
(d) any of the above
Ans: d
(a) total installed capacity of the plant
(b) sizes of the generating units
(c) operating schedule of generating units
(d) all of the above
Ans: d
(a) Solar power plant
(b) Tidal power plant
(c) Wind power plant
(d) Any of the above
Ans: d
(a) fuel cell
(b) batteries
(c) thermionic converter
(d) all of the above
Ans: c
(a) plant is used for stand by purpose only
(b) plant is under maintenance
(c) plant is used for base load only
(d) plant is used for peak load as well as base load
Ans: a
(a) Thermocouple
(b) Photovoltaic cell
(c) Solar cell
(d) Photoelectric cell
Ans: a
(a) Water
(b) Carbon tetrachloride fire extinguisher
(c) Foam type fire extinguisher
(d) CO2 fire extinguisher
Ans: b
(a) arc lamps
(b) induction motors
(c) fluorescent tubes
(d) incandescent lamp
Ans: d
(a) nuclear power plants
(b) hydraulic turbines
(e) diesel engines
(d) steam accumulators
(e) none of the above
Ans: c
(a) fuel cells
(b) solar cells
(c) MHD generators
(d) none of the above
Ans: c
(a) Narora
(b) Tarapur
(c) Kota
(d) Benglore
Ans: d
(a) system power factor is changed
(b) some loads are switched off
(c) system voltage is reduced
(d) system frequency is reduced Efficiency is the secondary consideration in
Ans: b
(a) Base load plants
(b) Peak load plants
(c) Both (a) and (b)
(d) none of the above
Ans: b
(a) Closed cycle gas turbine
(b) Open cycle gas turbine
(c) Diesel engine
(d) Petrol engine
Ans: a
(a) peak load plant
(b) base load plant
(c) stand-by plant
(d) spinning reserve plant
(e) any of the above
Ans: b
(a) Steam
(b) Diesel
(c) Hydroelectric
(d) Any of the above
Ans: c
(a) Hydroelectric
(b) Nuclear
(c) Steam
(d) Diesel
(e) Any of the above
Ans: d
(a) Fuel cost
(b) Interest on capital
(c) Depreciation
(d) Insurance charges
Ans: a
(a) Vacuum cleaner
(b) Television
(c) Hair dryer
(d) Electric shaver
Ans: d
(a) nuclear power plants
(b) diesel generating plants
(c) steam power stations
Ans: a
(a) Exhaust fan
(b) Lathe machine
(c) Welding transformer
(d) All of the above
Ans: c
(a) increased business activity
(b) increased water supply
(c) increased use of fans and air conditioners
(d) none of the above
Ans: c
(a) Hot reserve
(b) Cold reserve
(c) Spinning reserve
(d) Firm power
Ans: b
(a) firm power
(b) cold reserve
(c) hot reserve
(d) spinning reserve
Ans: d
(a) Television set
(b) Toaster
(c) Vacuum cleaner
(d) Washing machine
Ans: b
(a) Soap
(b) Sugar
(c) Vegetable oil
(d) Caustic soda
Ans: c
(a) Fuel cost
(b) Interest on capital
(c) Insurance charges
(d) Depreciation
Ans: a
(a) Diesel engine plant
(b) Nuclear power plant
(c) Gas turbine plant
(d) Pumped storage plant
Ans: b
(a) plant reserve capacity will be zero
(b) diversity factor will be unity
(c) load factor will be unity
(d) load factor will be nearly 60%
Ans: a
(a) diesel power plants
(b) nuclear power plants
(c) hydro-electric power plants
(d) thermal power plants
Ans: d
(a) Thermal power plant
(b) Diesel power plant
(c) Nuclear power plant
(d) Hydro-electric power plant
Ans: b
(a) Nuclear power plants
(b) Gas turbine power plants
(c) Solar power plants
(d) Hydro-electric power plants
Ans: a
(a) Nuclear power plant
(b) Hydro-electric power plants
(c) Thermal power plants
(d) Diesel engine power plants
Ans: c
(a) Nuclear power plant
(b) Steam turbine plant
(c) Pumped storage plant
(d) None of the above
Ans: c
(a) Maintenance cost
(b) Fuel cost
(c) Salaries of high officials
(d) Salaries of operating staff
Ans: c
(a) It should run at high speed
(b) It should produce high voltage
(c) It should be small in size
(d) It should be capable of starting quickly
Ans: d
(a) water cooled
(b) natural air cooled
(c) forced air cooled
(d) hydrogen cooled
Ans: d
(a) Phase advancers
(b) Synchronous compensators
(c) Static capacitors
(d) Any of the above
Ans: d
(a) rated r.p.m.
(b) no load
(c) 20 percent load
(d) near full load
(e) none of the above
Ans: d
(a) Poor voltage regulation
(b) Increased transmission losses
(c) High cost of equipment for a given load
(d) All of the above
Ans: d
(a) at the receiving end
(b) at the sending end
(c) either (a) or (b)
(d) none of the above
Ans: a
(a) kW
(b) kWh
(e) kVAR
(d) none of the above
Ans: c
(a) High maintenance cost
(b) Continuous losses in motor
(c) Noise
(d) All of the above
Ans: d
(a) 0.5 lagging
(b) 0.5 leading
(c) 0.95 lagging
(d) 0.95 leading
Ans: c
(a) Induction motor
(b) Under excited synchronous motor
(c) Over excited synchronous motor
(d) D.C. generator
(e) None of the above
Ans: c
(a) Cost of wages
(b) Cost of fuel
(c) Cost of lubricants
(d) All of the above
Ans: d
(a) remains unchanged
(b) decreases
(c) increases
(d) none of the above
Ans: c
(a) 25 to 50 percent full load
(b) 50 to 75 percent full load
(c) full load
(d) 25 percent overload
Ans: b
(a) Electric clock
(b) Mixer grinder
(c) Ceiling fan
(d) Room heater
Ans: d
(a) 5 kW
(b) 40 k\V
(c) 80 kW
(d) 120 kW
Ans: a
(a) Improved frequency of power supplied
(b) Reduction in total installed capacity
(c) Increased reliability
(d) Economy in operation of plants
Ans: a
(a) kW
(b) kVAR
(c) kWh
(d) kVA
Ans: d
(a) NTPC
(b) SAIL
(c) BEL
(d) BHEL
Ans: a
(a) peak load plants
(b) base load plants
(c) either (a) or (b)
(d) none of the above
Ans:
(a) 15 to 20 years
(b) 20 to 50 years
(c) 50 to 75 years
(d) 75 to 100 years
Ans: a
(a) Sinking fund method
(b) Straight line method
(c) Diminishing value method
(d) Halsey's 50—50 formula
Ans: d
(a) 15 years
(b) 30 years
(c) 60 years
(d) 100 years
Ans: d
(a) peak demand
(b) average demand
(c) diversified demand
(d) none of the above
Ans: a
(a) Solar energy
(b) Geothermal power
(c) Wind power
(d) iMHD
Ans:
(a) private sector
(b) public sector
(c) government sectors
(d) joint sector
(e) none of the above
Ans: b
(a) To excite the poles of main exciter
(b) To provide requisite starting torque to main exciter
(c) To provide requisite starting torque to generator
(d) None of the above
Ans: a
(a) induction motors
(b) synchronous motors
(c) single phase motors
(d) d.c. motors
Ans: a
(a) synchronous condenser
(b) generator
(c) induction motor
(d) alternator
Ans: a
(a) Little maintenance cost
(b) Ease in installation
(c) Low losses
(d) All of the above
Ans: d
(a) two part tariff
(b) three part tariff
(c) block rate tariff
(d) any of the above
Ans: b
(a) peak load plant
(b) casual run plant
(c) either (a) or (b)
(d) base load plant
Ans: c
(a) Diesel engine plant
(b) Gas turbine plant
(c) Nuclear power plant
(d) Pumped storage plant
Ans: c
(a) Steam turbine
(b) Condenser
(c) Water treatment plant
(d) Boiler
Ans: d
(a) Supercharged engine
(b) Diesel engine
(c) Petrol engine
(d) All of the above engines will equal power
Ans: c
(a) Diesel power plants
(b) Thermal power plants
(c) Hydro-electric power plants
(d) Nuclear power plants
Ans: a
(a) Steam accumulators
(b) Air motors
(c) Diesel engines
(d) Batteries
Ans: d
(a) diesel engine
(6) hydraulic turbine
(c) steam turbine
(d) gas turbine
Ans: b
(a) current
(b) voltage
(c) duration of contact
(d) all of the above
Ans: d
(a) Direct stroke on line conductor
(b) Indirect stroke on conductor
(c) Direct stroke on tower top
(d) Direct stroke on ground wire
Ans: a
(a) Horn gaps
(b) Rod gaps
(c) Surge absorbers
(d) All of the above
Ans: d
(a) Load shedding
(b) Power factor improvement at the , generators
(c) Penalising high load consumers by increasing the charges for electri¬city
(d) Efficient plant operation
Ans: a
(a) Switching of the loads
(b) Frequency reduction
(c) Voltage reduction
(d) Any of the above
Ans: d
(a) Unskilled workers only
(b) Skilled workers only
(c) Equipment only
(d) All of the above
Ans: d
(a) fixed deposits
(b) shares
(c) bonds
(d) any of the above
Ans: d
(a) Shares
(b) Fixed deposits
(c) Cash certificates
(d) Bonds
Ans: a
(a) plant capacity
(b) average load
(c) peak load
(d) kWh generated
(e) none of the above
Ans: a
(a) Easily damaged by high voltage
(b) Cannot be repaired
(c) Short service life
(d) All of the above
Ans: d